  • Question 111:

    If a project with a SPI of 0.8, what you tell?

    A. The project is running ahead of the schedule

    B. The project is running behind of the schedule

    C. Resources assigned to the project cost 1.8 units

    D. None

  • Question 112:

    You are creating your WBS and keep decomposing tasks into smaller units. How can you tell when you are done?

    A. Keep decomposing tasks until you reach an amount of work that is small enough to reliably estimate required resources and duration.

    B. Keep decomposing work until you reach a predetermined number of hierarchy levels to keep the WBS balanced.

    C. Keep decomposing tasks until you reach an amount of work that can be accomplished in one DAY.

    D. Keep decomposing tasks until you reach an amount of work that can be accomplished in one WEEK.

  • Question 113:

    How many communication channels will be required in a project in which 5 individual are participating?

    A. 10

    B. 12

    C. 4

    D. 5

  • Question 114:

    Acceptance of the product should be .

    A. Formal

    B. Consistent

    C. Personal

    D. Verbal

  • Question 115:

    is always the lowest risk for the buyer if the scope of work is not well defined.

    A. Cost plus incentive fee

    B. F'xed P|ice

    C. Time and material

    D. "'s^ 's nc* 'elated to price

  • Question 116:

    Who is responsibility for making sure that a message in the project team is understood?

    A. Project Manager

    B. Sender

    C. Project coordinator

    D. Sponsor

  • Question 117:

    The main purpose of project initiation is to .

    A. Assign the project manager to the project

    B. Formally describe the project

    C. Produce the project charter

    D. Formally authorize the project

  • Question 118:

    Project just went into inclusion mode. This means that project .

    A. Has become part of the business processes

    B. Has been accepted by the sponsor and the client

    C. Will be closed due to lack of resources

    D. None of the above

  • Question 119:

    Which document formally authorizes a project?

    A. The project charter

    B. Project scope statement

    C. The P'oject contract

    D. Project closing document

  • Question 120:

    The main purpose of project initiation is to .

    A. Assign the project manager to the project

    B. Formally describe the project

    C. Produce the project charter

    D. Formally authorize the project

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CA0-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.