Q41
Single choice
MANAGING PRODUCT DELIVERY
The team manager for the production of the `marketing materials' has identified that they will not be ready
within the timescale agreed in the work package. The team manager has sufficient tolerance to take corrective action. As a result, additional resources have been assigned to this work package.
Which theme is being applied?