Q19 Single choice Mark for later Which of the following activities is the Executive responsible for? A Ensure the desired outcome of the project is specified B Responsible for the benefits review plan C Assess and update the Business Case at the end of each stage D Responsible for the Benefits Review Plan post project Correct answer