Question 18 of 50
0% complete
Q18 Single choice

The Health and Safety Training Project is following ABC Company's standard course development model.
This model is updated regularly by the company's centre of excellence based on feedback from projects at key stages throughout the project lifecycle. During the 'starting up a project' process, the centre of excellence provided the Health and Safety Training project manager with the latest version of the model.

Which principle is being applied, and why?