Question 34 of 50
0% complete
Q34 Single choice

During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course. The change to project scope was approved and the cost of ?,500 was paid for from the change budget. The project manager documented an increase of ?,500 in the project budget in the business case.

Is this an appropriate action, and why?