Q94 Single choice Mark for later Which project board decision supports the 'manage by stages' principle? A Authorizing a request for change during a stage B Authorizing implementation of the next delivery stage C Authorizing an exception plan after an exception report D Authorizing a concession following an off-specification Correct answer