Q56 Single choice Mark for later The creation of an Exception Plan often follows which situation? A A time or cost slippage occurs during a management stage B An Exception Report being submitted to the Project Board C A Stage Plan is updated due to an urgent corrective action being taken D An Issue Report being created Correct answer