Q5 Single choice Mark for later Which describes a time-driven control? A The dates for the project's end stage assessment included in the project plan B The expected frequency of progress reports specified in a work package C The expected dates for planned checks of specialist products included in a stage plan D The planned exception assessment meeting to authorize a requested exception plan Correct answer