Q23 Single choice Mark for later Which feature of a stage plan suggests that a project is in danger of scope creep? A Stage plans are prepared by the project manager as the stage comes to an end B Products identified in a stage plan cannot be traced back to the project plan C The team delivering the stage plan includes staff from different parts of an organization D It is not possible to implement remedial actions for an exception by updating a stage plan Correct answer