Question 251:
Which two activities will a Product Owner engage in during a Sprint? (Choose two.)
A. Run the Daily Scrum. B. Prioritize the Development Team's work on the Sprint Backlog. C. Update the Sprint burndown chart. D. Answer questions from the Development Team about items in the current Sprint. E. Work with the stakeholders.
D. Answer questions from the Development Team about items in the current Sprint. E. Work with the stakeholders.
Question 252:
How should a Development Team deal with non-functional requirements?
A. Ensure every Increment meets them. B. Make sure the release department understands these requirements, but it is not the Development Team's responsibility. C. Handle them during the Integration Sprint preceding the Release Sprint. D. Assign them to the lead developers on the team.
A. Ensure every Increment meets them.
Question 253:
A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation? (Choose two.)
A. Discuss the impediments with the Development Team. B. Prioritize the list and work on them in order. C. Arrange a triage meeting with all project managers. D. Add each open impediment to the Product Backlog.
A. Discuss the impediments with the Development Team. B. Prioritize the list and work on them in order.
Question 254:
Who is responsible for engaging the stakeholders?
A. The Business Analyst. B. The Development Team. C. The Team Manager. D. The Project Manager. E. The Product Owner.
E. The Product Owner. https://agility.im/frequent-agile-question/how-do-scrum-teams-work-with-stakeholders-and-customers/#:~:text=In%20Scrum%2C%20the%20product%20owner,%3B%20ultimately%2C%20they%20remain%20accountable
Question 255:
Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
A. True B. False
A. True https://www.scrum.org/forum/scrum-forum/43558/multiple-scrum-teams-must-use-same-sprint-start-date-same-product
Question 256:
Which approach is best for Scrum Teams in order to produce valuable Increments?
A. Each Developer works on the component where they feel that they can contribute. B. Each Scrum Team is accountable for developing functionality from beginning to end. C. Each Scrum Team works on an independent set of components. D. Each Scrum Member works only as an independent layer of the system.
B. Each Scrum Team is accountable for developing functionality from beginning to end. https://www.atlassian.com/agile/scrum/roles
Question 257:
What does it mean for a Scrum Team to be cross-functional?
A. The Scrum Team includes not only developers but also business analysts, architects, and testers. B. The Scrum Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment. C. Developers on the Scrum Team work closely with business analysts, architects, developers and testers who are not on the team. D. The Scrum Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers.
B. The Scrum Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment.
Question 258:
When is it most appropriate for a Scrum Team to change the Definition of Done?
A. Prior to starting a new project. B. During Product Backlog refinement. C. During Sprint Planning. D. During the Sprint Retrospective.
C. During Sprint Planning.
Question 259:
If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
A. The evolution of the cost spent on the project. B. When all work will be completed to the Scrum Team can be released for other work. C. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team. D. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.
C. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team. https://www.knowledgehut.com/tutorials/scrum-tutorial/sprint-burndown-chart
Question 260:
When can a Development Team cancel a Sprint?
A. It can't. Only Product Owners can cancel Sprints. B. When functional expectations are not well understood. C. When the Product Owner is absent too often. D. When the selected Product Backlog items for the Sprint become unachievable. E. When a technical dependency cannot be resolved.
A. It can't. Only Product Owners can cancel Sprints. Explanation Explanation/Reference:https://scrumguides.org/scrum-guide.html#:~:text=A%20Sprint%20could%20be%20cancelled,authority%20to%20cancel%20the%20Sprint
Nowadays, the certification exams become more and more important and required by more and more
enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare
for the exam in a short time with less efforts? How to get a ideal result and how to find the
most reliable resources? Here on Vcedump.com, you will find all the answers.
Vcedump.com provide not only Scrum exam questions,
answers and explanations but also complete assistance on your exam preparation and certification
application. If you are confused on your PSM-I exam preparations
and Scrum certification application, do not hesitate to visit our
Vcedump.com to find your solutions here.