  • Question 191:

    A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items "Done" by the end of the Sprint. Which three phrases best describe the purpose of a definition of "Done"? (Choose three.)

    A. It controls whether the developers have performed their tasks.

    B. It provides a template for elements that need to be included in the technical documentation.

    C. It creates transparency over the work inspected at the Sprint Review.

    D. It trucks the percent completeness of a Product Backlog item.

    E. It guides the Development Team is creating a forecast at the Sprint Planning.

    F. It defines what it takes for an Increment to be ready for release.

  • Question 192:

    You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)

    A. Introduce a bonus system for the top performers in the team.

    B. Have the Scrum Team members introduce themselves to each other and give a brief background of their skills and work history.

    C. Have the development managers for each Development Team member introduce their direct reports and go over their responsibilities on the Scrum Team.

    D. Ensure the Scrum Team members have compatible personalities.

    E. Ensure the team understands they need a definition of "Done".

    F. Ask the Product Owner to discuss the product or project, its history, goals, and context, as well as answer questions.

  • Question 193:

    Who creates a Product Backlog Item's estimate?

    A. The Development Team after clarifying requirements with the Product Owner.

    B. The Product Owner with input from the Development Team.

    C. The most senior people in the organization, including architects and subject matter experts.

    D. The Scrum Master.

    E. The Development Team, alone.

  • Question 194:

    Who starts the Daily Scrum?

    A. The person coming in last. This encourages people to be on time and helps to stay within the time-box.

    B. Whoever the Development Team decides should start.

    C. The person who has the token.

    D. The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

    E. The person who last broke the build.

  • Question 195:

    Which Scrum Values are violated by building Product Backlog items that have low business value? (Choose three.)

    A. Economic Value Added.

    B. Respect.

    C. Focus.

    D. Earned Value.

    E. Courage.

  • Question 196:

    The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

    A. Opportunities to inspect and adapt the Sprint Backlog are lost.

    B. Impediments are raised and resolved more slowly.

    C. The Product Owner cannot accurately report progress to the stakeholders.

    D. Too much work is spent updating the Scrum board before the meeting.

    E. The Scrum Master loses the ability to update the Gantt chart properly.

    F. The Sprint plan may become inaccurate.

  • Question 197:

    Which statement best describes Scrum?

    A. A defined and predictive process that conforms to the principles of Scientific Management.

    B. A complete methodology that defines how to develop software.

    C. A cookbook that defines best practices for software development.

    D. A framework within which complex products in complex environments are developed.

  • Question 198:

    When is it most appropriate for a Development Team to change the definition of "Done"?

    A. During Spring Planning.

    B. Prior to starting a new Sprint.

    C. During the Sprint Retrospective.

    D. Prior to starting a new project.

  • Question 199:

    Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

    A. The Project Manager.

    B. The Product Owner.

    C. The Scrum Master.

    D. The Development Team.

    E. All of the above.

  • Question 200:

    How often should Scrum Team membership change?

    A. As needed, while taking into account a short term reduction in productivity.

    B. Never, because it reduces productivity.

    C. As needed, with no special allowance for changes in productivity.

    D. Every Sprint to promote shared learning.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scrum exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PSM-I exam preparations and Scrum certification application, do not hesitate to visit our Vcedump.com to find your solutions here.