Question 131:
Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)
A. How is the Sprint proceeding? B. What did I do yesterday that helped the Development Team meet the Sprint Goal? C. Why were you late? D. What will I do today to help the Development Team meet the Sprint Goal? E. How many hours did I spend on the project yesterday? F. What will I be working on tomorrow? G. Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?
B. What did I do yesterday that helped the Development Team meet the Sprint Goal? D. What will I do today to help the Development Team meet the Sprint Goal? G. Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?
Question 132:
The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)
A. Inform the Product Owner's functional manager. B. Stop the Sprint, send the Product Owner to a course and restart. C. Bring up the problem in the Sprint Retrospective. D. Coach the Product Owner in the values of Scrum and incremental delivery. E. Nominate a proxy Product Owner.
C. Bring up the problem in the Sprint Retrospective. D. Coach the Product Owner in the values of Scrum and incremental delivery.
Question 133:
Who can abnormally terminate a Sprint?
A. The Scrum Master B. The Development Team or its members. C. The Product Owner D. The Stakeholders
C. The Product Owner https://3back.com/scrum-tips/abnormal-termination-of-a-sprint/#:~:text=Not%20only%20can%20the%20Product,Scrum%20from%20the%20very%20beginning
Question 134:
During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
A. When the Product Owner identifies new work. B. As soon as possible after they are identified. C. When the Scrum Master has time to enter them. D. During the Daily Scrum after the Development Team approves them.
B. As soon as possible after they are identified.
Question 135:
What is the accountability of the Product Owner during Sprint 0?
A. There is no such thing as Sprint 0. B. Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog. C. Make the complete project plan to commit date, budget, and scope to the stakeholders. D. Determine the composition of the Development Teams so they have the capacity to deliver the completed forecast. E. Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
A. There is no such thing as Sprint 0. https://www.scrum.org/resources/blog/scrum-myths-it-ok-have-sprint-0-design-sprint-hardening-sprint
Question 136:
Who creates the Definition of Done?
A. The Scrum Team B. The Scrum Master C. The Product Owner D. The Developers
A. The Scrum Team
Question 137:
Who should know the most about the progress toward a business objective or a release?
A. The Project Manager. B. The Scrum Master. C. The Development Team. D. The Product Owner.
D. The Product Owner. https://www.scruminc.com/product-goal/
Question 138:
Scrum is a methodology that tells in detail how to build software incrementally.
A. True B. False
B. False https://www.scrum.org/resources/what-is-scrum
Question 139:
The Product Backlog is ordered by:
A. The Product Owner with the most valuable items placed at the top. B. Risk, where safer items are at the top, and riskier items are at the bottom. C. Items are randomly arranged. D. Size, where small items are at the top and large items are at the bottom.
A. The Product Owner with the most valuable items placed at the top. https://berteig.com/how-to-apply-agile/scrum-rules-the-product-backlog-is-ordered-by-the-product-owner/
Question 140:
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what "Done" means. (Choose two.)
A. All work the Development Team is willing to do. B. Ready for integration. C. No work left from the definition of "Done". D. Whatever the Product Owner defines as quality. E. All work to create software that is ready to be released to end users.
C. No work left from the definition of "Done". E. All work to create software that is ready to be released to end users.
Nowadays, the certification exams become more and more important and required by more and more
enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare
for the exam in a short time with less efforts? How to get a ideal result and how to find the
most reliable resources? Here on Vcedump.com, you will find all the answers.
Vcedump.com provide not only Scrum exam questions,
answers and explanations but also complete assistance on your exam preparation and certification
application. If you are confused on your PSM-I exam preparations
and Scrum certification application, do not hesitate to visit our
Vcedump.com to find your solutions here.