PRINCE2-FOUNDATION Exam Details

  • Exam Code
    :PRINCE2-FOUNDATION
  • Exam Name
    :PRINCE2 Foundation
  • Certification
    :PRINCE2 Certifications
  • Vendor
    :PRINCE2
  • Total Questions
    :1158 Q&As
  • Last Updated
    :May 25, 2026

PRINCE2 PRINCE2-FOUNDATION Online Questions & Answers

  • Question 71:

    What is a responsibility of the business representative on the Project Board?

    A. Setting tolerance levels for the project
    B. Ensuring the project represents value for money
    C. Confirming the project delivers the required functionality
    D. Checking the required quality levels are achieved by the project's products

  • Question 72:

    Which PRINCE2 role has a specific responsibility for advising on the selection of the development strategy, design and methods?

    A. Project Manager
    B. Quality Assurance
    C. Team Manager
    D. Project Assurance

  • Question 73:

    Are the following statements regarding raising exceptions true or false?

    1.

    If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue Report to capture and analyze the details of the deviation

    2.

    Where a Work Package is forecast to exceed its tolerances, the Project Manager may request the Team Manager to produce an Exception Plan

    A. Only 1 is true
    B. Only 2 is true
    C. Both 1 and 2 are true
    D. Both 1 and 2 are false

  • Question 74:

    What product identifies the management stages and other major control points in a project?

    A. Business Case
    B. Project Plan
    C. Work Package
    D. Project Brief

  • Question 75:

    What is the assessed risk probability used to identify?

    A. The responsibilities for managing and implementing a particular risk
    B. The likely effect that a risk has on the project delivering its objectives
    C. The timeframe within which the risk may occur
    D. The decision-making body to whom the risk should the referred

  • Question 76:

    Which role is part of the project management team?

    A. Change Authority
    B. Stakeholder
    C. Quality assurance
    D. Corporate or programme management

  • Question 77:

    What type of progress control is a Checkpoint Report?

    A. Event-driven
    B. Exception-based
    C. Time-driven
    D. Ad hoc-based

  • Question 78:

    Which is a purpose of the Controlling a Stage process?

    A. Produce a Team Plan for the work to be assigned to a Team Manager
    B. Select and implement actions that will resolve deviations from a plan within tolerance
    C. Obtain approvals for products delivered in aWork Package D. Update a Project Plan to incorporate the actuals from a Stage Plan

  • Question 79:

    Which is a task of product-based planning?

    A. Design the plan
    B. Create the product flow diagram
    C. Analyze the risks
    D. Prepare the schedule

  • Question 80:

    What theme establishes the mechanisms to judge whether a project is worthwhile investing in?

    A. Plans
    B. BusinessCase
    C. Risk
    D. Quality

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.