PRINCE2 PRINCE2-FOUNDATION Online Questions & Answers

  • Question 61:

    Which product would document any unfinished work, ongoing issues and risks?

    A. Project closure notification
    B. Lessons Report
    C. End Project Report
    D. Risk Register

  • Question 62:

    Whose approval is needed to replace a Stage Plan with an Exception Plan?

    A. Corporate orprogramme management
    B. Project Board
    C. Project Manager
    D. Team Manager

  • Question 63:

    Which PRINCE2 principle is being applied when effective project controls are established?

    A. Learn from experience
    B. Manage by exception
    C. Focus on products
    D. Defined roles and responsibilities

  • Question 64:

    Which products, identified when creating a product breakdown structure, should each have a corresponding entry in the Risk Register?

    A. Those that have been completed, but have NOT been quality checked
    B. Those that have been broken down into sub-products
    C. Those to be created outside the scope of the project
    D. Those dependent on more than one other product

  • Question 65:

    Which of the following is an objective of a quality review?

    A. Provide an opportunity to change the product
    B. Provide sufficient information to perform a performance review on the Producer
    C. Provide confirmation that the product is complete and ready to be approved
    D. Allow the Project Manager to delegate more quality checking responsibility to the Team Manager

  • Question 66:

    What term describes a period of time for which it is possible to produce a plan accurately?

    A. Critical path
    B. Delivery step
    C. Management stage
    D. Planning horizon

  • Question 67:

    Which is an objective of the `managing a stage boundary' process?

    A. To manage risks and issues that may impact the current stage
    B. To prepare an exception plan as directed by the project board
    C. To define how and when all the project's products will be delivered and at what cost
    D. To control the delivery of the project's products

  • Question 68:

    Any project outcomes perceived as negative by one or more stakeholders would be documented in which product?

    A. Risk Management Strategy
    B. Issue Register
    C. Business Case
    D. Project Product Description

  • Question 69:

    Identify the missing words in the following sentence. The Project Board will allocate tolerances [ ? ] to the Project Manager.

    A. for each Work Package
    B. for the project
    C. for each management stage
    D. for each technical stage

  • Question 70:

    Which of the following project management team roles can be shared?

    1.

    Project Assurance

    2.

    Executive

    3.

    Senior User

    4.

    Senior Supplier

    A. 1,2,3
    B. 1,3,4
    C. 2,3,4
    D. 1,2,4

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.