Which statement is true regarding stakeholders?
A. The Senior Supplier is NOT a stakeholder
B. All stakeholders must be identified during project initiation
C. Stakeholders are always external to the corporate organization
D. All three primary categories of stakeholder have their interests represented by the Project Board
Within the PRINCE2 customer/supplier environment, what is a supplier responsibility?
A. Define what the acceptance criteria are for the project product
B. Ensure the resources are made available to deliver the required result
C. Secure the funding for the project
D. Specify the desired project outcomes
For whom does the Senior User make decisions on behalf of?
A. Those who will provide the necessary skills to produce the project product
B. Those who will operate and maintain the project's products
C. Those with an interest in how the project meets a business need
D. Quality Assurance
Which role is the key decision-maker on the project management team?
A. Corporate or programme management
B. Change Authority
C. Project Manager
D. Executive
Which theme includes the estimating of the effort required to develop the project's products?
A. Plans
B. Progress
C. Business Case
D. Organization
Which role would represent the interests of the people who will be operating the project's products?
A. Senior Supplier
B. Executive
C. Change Authority
D. Senior User
During project initiation, who determines the use of a Change Authority and whether a change budget will be used?
A. Project Board
B. Change Authority
C. Project Manager
D. Corporate or Programme Management
Which of the following would help to define the project's products and show the sequence in which those products are to be created?
A. Writing Product Descriptions
B. Product-based planning technique
C. Creating a product breakdown structure
D. Writing a Project Product Description
What is the first task of the product-based planning technique?
A. Identify activities and dependencies
B. Write Product Descriptions
C. Create a product breakdown structure
D. Write the Project Product Description
Which of the following statements are true regarding the product-based planning technique?
1.
Product Descriptions show the hierarchy of a Plan's products
2.
Identifying activities and dependencies is a key task of product-based planning
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Both 1 and 2 are false
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.