  • Question 141:

    Which product should be continuously maintained regarding the status, history and version of a product?

    A. Stage Plan

    B. Configuration Item Record

    C. Highlight Report

    D. Product Status Account

  • Question 142:

    Which product would be updated to show that a decision has been made to accept an off- specification?

    A. Quality Register

    B. Daily Log

    C. Issue Report

    D. Risk Register

  • Question 143:

    If a product's weight was specified to be 300 grams, but could only be built to a weight of 400 grams, which of the following would be created?

    A. Exception Plan

    B. Request for change

    C. Off-specification

    D. Exception Report

  • Question 144:

    Which of the following are types of issue?

    1.

    Concession

    2.

    Off-specification

    3.

    Request for change

    4.

    Problem/concern

    A. 1,2,3

    B. 2,3,4

    C. 1,2,4

    D. 1,3,4

  • Question 145:

    Which is a purpose of a Configuration Management Strategy?

    A. Provide details for each configuration item and any important relationships between them

    B. Define the composition and format of all the projects registers and logs

    C. Identify who will set up and manage the Quality Register

    D. Define how the products and various versions will be identified

  • Question 146:

    Who are allowed to raise issues?

    A. Only the Project Manager and Team Manager

    B. Anyone with an interest in the project or its outcome

    C. Only the Change Authority

    D. Only members of the project management team

  • Question 147:

    Which of the following is a typical activity of a configuration management procedure?

    A. Communicate

    B. Status accounting

    C. Impact assessment

    D. Implement

  • Question 148:

    Which of the following is NOT a typical activity of a configuration management procedure?

    A. Communicate

    B. Control

    C. Identification

    D. Planning

  • Question 149:

    Which of the following is a request for change?

    A. The Executive feels that the project product may not be of sufficient quality in order to achieve the expected benefits

    B. The Project Manager has been advised that a team member has been taken ill and so the end date of the work will now be delayed by 5 days

    C. The supplier needs to amend a product because it does not conform to its quality criteria

    D. Although it has passed quality control, a user would like to suggest an increase in the durability of a product

  • Question 150:

    According to PRINCE2, the quality review technique compliments the use of which of the following?

    A. Product Descriptions

    B. Quality Assurance

    C. Issue and change control procedure

    D. Customer's quality expectations

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.