  • Question 1:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely. There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?

    A. Issue Register

    B. Follow-on action recommendations

    C. Lessons Report

    D. Risk Register

  • Question 2:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely. There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?

    A. Benefits Review Plan

    B. Exception Report

    C. End Project Report

    D. Risk Register

  • Question 3:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely. There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should show that the project has been closed prematurely and has not achieved the objectives defined in the Project Initiation Documentation (PID)?

    A. Benefits Review Plan

    B. End Project Report

    C. Exception Report

    D. Project closure notification

  • Question 4:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely. There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?

    A. Benefits Review Plan

    B. End Project Report

    C. Follow-on action recommendations

    D. Project closure notification

  • Question 5:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely. There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should show that the staff photo sessions were disruptive to the Engineering Department as they had been scheduled during peak work times without consultation with the Engineering Manager?

    A. Follow-on action recommendations

    B. Lessons Report

    C. Project closure notification

    D. Risk Register

  • Question 6:

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for

    the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to

    the Project Board is to close the project prematurely.

    There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.

    Which product should show that the photos could be used for other promotional material for the company?

    A. Benefits Review Plan

    B. Lessons Log

    C. Exception Report

    D. End Project Report

  • Question 7:

    Which principle is supported by the activity Evaluate the Project?

    A. Continued Business Justification

    B. Defined roles and responsibilities

    C. Learn from experience

    D. Manage by stages

  • Question 8:

    Which of the following activities is NOT an action of preparing for planned closure?

    A. Update the project plan with actual

    B. Update the Project Management Team

    C. Request a product status account

    D. Confirm project has delivered what is defined in Project Product Description

  • Question 9:

    Which of the following statements is FALSE regarding the Continued Business Justification?

    A. The justification for the project must remain the same throughout the project.

    B. The justification for the project should remain vabd.

    C. The justification for the project may change.

    D. If the project is no longer justified it should be stopped.

  • Question 10:

    Which of the following activities could trigger the production of an exception plan?

    A. Review Stage status

    B. Giving ad hoc direction

    C. Escalating a project issue

    D. Report stage end

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2P exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.