A product team is comprised of consultants and staff members. Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management. What should the project manager do?
A. Reject the risk because the team is not in agreement on escalating it.Product implementation portions of a project are nearing completion. The project manager schedules a series of meetings to meet with the marketing management team. During the meeting, the marketing manager tells the project manager that some key members of the department will not be available to work on the implementation for the next 3 months.
What should the project manager do?
A. Shift those key members and assign them to another project.A company hired a new project lead to incorporate some agile practices. Which three changes should the project lead incorporate in the existing team meetings? (Choose three)
A. Add sprints and sprint reviews as necessary.A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members. The project manager tells the new team member to align with the team's principles and arrive on time. What kind of conflict resolution did the project manager apply in this situation?
A. Smooth/accommodateDuring a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work. The customer is asking the project manager for guidance. What should the project manager do?
A. Wait to start the project execution phase until all requirements and acceptance criteria are clear.A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.
Which project approach suits the scenario?
A. Execute it as a Scrum projectDuring an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy. What should the project manager share with the key resource?
A. The updated benefits management planAn agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A. Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule. What should the project manager do?
A. Adopt the same timeframe as the closed project for the current project.A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach. What should the project manager do to ensure full compliance of quality requirements during the execution phase?
A. Analyze the quality requirements.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.