A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved. How should the project manager proceed?
A. Proceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvalsIn the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant. What should the project manager do next?
A. Evaluate the impact of nonrenewal of the license.A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue. What should the project manager do to encourage the team?
A. Schedule training courses to enhance team performance.The project manager has observed that two team members have been arguing with each other openly at meetings. To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members.
What two actions should project manager take? (Choose two.)
A. Ask the team members to work it out themselvesAn agile team is struggling to successfully deliver what they have committed. During the daily status meetings, the project manager notices that the most senior engineer is doing all of the talking, leaving little time for the other members to share their status. The team's performance is not good, and some team members want to leave the team.
How should the project manager approach this situation?
A. Measure the team's psychological safety.A project manager notices a conflict in the team on both technical and interpersonal levels during the execution phase of a project. What should the project manager do?
A. Hold a team meeting to understand and address the conflict.A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A. Recognize the stakeholder's skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.A project manager is leading a project at a contracting company, and the project team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.
What should the project manager do to avoid this situation in the future?
A. Manage the scope baseline to influence the factors that drive change.A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.
What should the project manager do?
A. Advise the team to continue their work as planned because the schedule cannot be changed.A team member is frustrated, thinking that their performance is below average since they have not completed as many items as other team members. The team member has become negative and disengaged, bringing team collaboration and productivity down.
What should the project manager do to increase the team's performance?
A. Meet with the team members and highlight individual contributions to encourage competition among the team.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.