A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks. What should the project manager do?
A. Create a new standard performance measure based on project requirements.A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project time lines have slipped, and the staff is overwhelmed. What should the project manager do to help the company meet their financial objectives?
A. Prioritize the projects, giving higher priority to projects that will increase profit.A project team has identified a risk and wants to accept it as an opportunity to finish a project earlier than planned. The project manager realizes that the sponsor may not accept the risk since the sponsor is risk averse. What should the project manager do?
A. Create a contingency reserve to cover the risk in order to ensure that the risk will be accepted.A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget. What should the project manager do?
A. Use the existing budget for executing the fallback plan and update the baseline.A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances. Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder.
What should the project manager do to resolve the team member's concerns?
A. Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to outline situations, solutions, results, and suggestions. How should the project manager use the information collected?
A. Map the lessons learned against work breakdown structure (WBS) components.During the design phase, a project manager realizes that the project will benefit from using adaptive tools. The effectiveness of this approach has been proven in past projects inside the organization. What should the project manager do first?
A. Update project documents to include adaptive tools and artifacts and plan the first iterative sessionAn ongoing project is facing a challenging situation in which the customer is not satisfied. The team is new to agile development, communicates frequently with the customer, and provides regular status reports.
What should the project lead do to satisfy the customer?
A. Schedule a meeting with the customer and explain that the team is new to agile and that the situation will improve.A project manager for a large software delivery project is in the process of finalizing the project governance. The project manager would like to implement procedures that do not align with several policies required by the organization's project
management office (PMO).
The project manager believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the technology.
What should the project manager do?
A. Engage stakeholders to modify policies outlined by the PMO.The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete. What should the project manager do?
A. Seek expert legal advice on the interpretation of the clauses in the contractNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.