A project manager recently took over an ongoing project. Within a few weeks, the project manager discovers that there are continuous change requests from different project end users.
What is the probable cause of this?
A. Undefined change control processA company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint, the project manager notices that the team is not working as a cohesive unit. Which two rules are appropriate for the project manager to instill in the team? (Choose two.)
A. Strive toward continuous improvementA new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company's biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately.
How should the project manager approach the software development life cycle with this customer?
A. Raise a risk that the scoping and estimating phase of the project will be delayed if the customer cannot deliver an approved set of requirements.During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining. What should the project manager do?
A. Work with the team to understand and solve the issues.A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.
What should the project manager do to communicate with the stakeholders?
A. Provide updates to the project sponsor to review and distribute to each stakeholder.During a project review session with key stakeholders, a senior manager raises a concern that the product being shown is not meeting the client's expectations. The project manager has noticed that although the team is meeting project deadlines, there are a large number of open quality issues that have not been addressed.
What should the project manager do?
A. Meet with the project stakeholders to review the scope and ask for a time extension to address the quality issues.During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?
A. Raise the risk of having the velocity impacted for the current iteration and discuss it with the product owner.A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software. What should the project manager do next?
A. Engage with the functional manager to discuss details to obtain the required support.During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget. What should the project manager do first?
A. Ask upper management for more funds and update the project budgetA project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?
A. Register the issue as a risk with the project team members.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.