You are the project manager of the GHQ project for your company. You are working with your project team to prepare for the qualitative risk analysis process. Mary, a project team member, does not understand why you need to complete qualitative risks analysis. You explain to Mary that qualitative risks analysis helps you determine which risks needs additional analysis. There are also some other benefits that qualitative risks analysis can do for the project. Which one of the following is NOT an accomplishment of the qualitative risk analysis process?
A. Corresponding impact on project objectivesTwo companies merge. The executive leadership team for the newly formed company hires a project risk manager to integrate both companies' technology platforms into a single global platform. Since success of this integration project is
critical for the new company, the project risk manager determines that risk management is vital.
What factors does risk response planning include?
A. People, planning, and analysisYou are a risk auditor for your company. You are reviewing the contract types a project manager has used in her project. Of the following, which contract type has the most risk for the project manager as a buyer?
A. Cost plus percentage of costsPete works as a project manager for BlueWell Inc. The Management has told him that he must implement an agreed-upon contingency response if the cost performance index in his project is less than 0.90. Consider that Pete's project has a budget at completion of $275,000. His project is 65 percent complete and he has spent $175,000 to date. However, Pete is scheduled to be 78 percent complete. What is the cost performance index for this project to determine if the contingency response should happen?
A. 1.02During what process should a project manager assign a risk owner?
A. Plan Risk ResponsesExamine the figure given below.

What will be the expected monetary value of Risk C?
A. -$113,750What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?
A. Organizational communication requirementsRob is the project manager of the IDLK Project for his company. This project has a budget of $5,600,000 and is expected to last 18 months. Rob has learned that a new law may affect how the project is allowed to proceed - even though the organization has already invested over $750,000 in the project. What risk response is the most appropriate for this instance?
A. AcceptanceManagement has asked you to perform a risk audit and report back on the results. Bonny, a project team member asks you what a risk audit is. What do you tell Bonny?
A. A risk audit is a review of all the risks that have yet to occur and what their probability of happening are.A project team working on a large software deployment project for a few months has been able to prevent a technical risk from occurring. However, an incident took place and triggered the technical issue. What should the risk manager do?
A. Execute the risk response plan defined for the risk.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.