  • Question 461:

    A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

    A. Synchronous
    B. Informal
    C. Asynchronous
    D. Formal

  • Question 462:

    A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

    A. Avoid
    B. Transfer
    C. Accept
    D. Share

  • Question 463:

    During the project initiation phase, a project manager needs to construct a project schedule and show the project dependencies. Which of the following should the project manager use for this task?

    A. Waterfall method
    B. Simulation method
    C. Precedence diagramming method
    D. Cost ratio analysis

  • Question 464:

    A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

    A. Status report
    B. Project plan
    C. Change log
    D. Meeting minutes

  • Question 465:

    Which of the following would be considered operational security?

    A. Mobile device compliance
    B. Background screening
    C. Multifactor authentication
    D. Facility access

  • Question 466:

    A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

    A. Make an impact assessment.
    B. Prepare a new purchase order.
    C. Select a new vendor.
    D. Create a risk register.

  • Question 467:

    Some project deliverables are behind schedule because adequate resources are not available to finish tasks in the set timeline.

    Which of the following should the project manager use to document this in formation?

    A. Time-tracking tools
    B. Issue log
    C. Status report
    D. Task board

  • Question 468:

    Given the following chart:

    Which of the following best describes the status of the project on Day 5?

    A. The sprint is complete.
    B. The project is ready for gate review.
    C. The project is on time.
    D. The project is behind schedule.

  • Question 469:

    A principle states 80% of the issues are the result of 20% of the causes. Which of the following types of diagrams is based on this principle?

    A. Pareto
    B. Scatter
    C. Network
    D. Fishbone

  • Question 470:

    A PM is evaluating whether an IaaS contract needs to be extended. When reviewing the system usage report, the PM realizes that usage is at 20% capacity.

    Which of the following actions should the PM take?

    A. Continue to monitor the system performance.
    B. Resize the resource utilization to reflect current needs.
    C. Reinforce adoption over time.
    D. Raise an item in the issue log.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.