  • Question 401:

    A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

    A. IaaS
    B. XaaS
    C. DaaS
    D. SaaS

  • Question 402:

    A project manager will be meeting with key stakeholders to give an update on the project. The attendees are all working remotely.

    Which of the following tools should the project manager use to conduct the meeting?

    A. Videoconferencing
    B. Telephone
    C. Whiteboard
    D. Word processing

  • Question 403:

    During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

    A. Project dashboard
    B. Gap analysis
    C. Risk register
    D. Communication plan

  • Question 404:

    The sales department accidentally has access to all project files, including employee personal information.

    Which of the following security concepts is this violating?

    A. Need-to-know
    B. Intellectual property
    C. Multifactor authentication
    D. Facility access

  • Question 405:

    A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

    A. Secure folder
    B. Real-time, multiauthoring editing software
    C. Digital whiteboard
    D. Wiki knowledge base

  • Question 406:

    A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

    A. Initiation
    B. Closing
    C. Execution
    D. Planning

  • Question 407:

    A company is working on a software development project that involves an external customer. Which of the following describes a project manager's responsibility within this type of project?

    A. Manage the project schedule.
    B. Define the functional requirements.
    C. Develop components for the software.
    D. Assess and authorize security policies.

  • Question 408:

    During an audit, a project manager finds out that a contractor exceeded the overtime hours allowed by the contract. Which of the following tools should the PM use to share the details with the management team?

    A. Time-tracking log
    B. Issue log
    C. Statement of work
    D. Risk register

  • Question 409:

    A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

    A. 9 days and $3,000
    B. 10 days and $3,200
    C. 12 days and $3,800
    D. 14 days and $4,000

  • Question 410:

    A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

    A. Performing
    B. Adjourning
    C. Forming
    D. Norming

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.