  • Question 151:

    By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

    A. Allocate resources.

    B. Determine the project budget.

    C. Develop a communication plan.

    D. Establish baselines.

  • Question 152:

    A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

    A. Trigger the contingency plan and communicate with the stakeholders.

    B. Work with the functional managers to create a work-around.

    C. Submit a change request to the change control board.

    D. Transfer the risk by hiring a new vendor who was successful on a previous project.

    E. Set up an escalation meeting with the sponsor.

  • Question 153:

    As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

    A. Update the work breakdown structure.

    B. Review the backlog.

    C. Seek baseline approval.

    D. Establish the resource pool.

  • Question 154:

    A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

    A. Synchronous

    B. Informal

    C. Asynchronous

    D. Formal

  • Question 155:

    Which of the following BEST describes how an organization should coordinate management of multiple related projects?

    A. Apply the SDLC process.

    B. Establish a program.

    C. Consult the CCB.

    D. Use different frameworks.

  • Question 156:

    A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

    A. Status report

    B. Project plan

    C. Change log

    D. Meeting minutes

  • Question 157:

    During a quality analysis review, the causes of several issues have been highlighted.

    Which of the following should the project manager use to identify the MOST important causes?

    A. Ishikawa diagram

    B. Scatter diagram

    C. Pareto chart

    D. Decision tree

  • Question 158:

    Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

    A. Evaluating the project

    B. Releasing the resources

    C. Closing the contracts

    D. Reconciling the budget

  • Question 159:

    Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

    A. Daily stand-up

    B. Project momentum

    C. Performance feedback

    D. Meeting minutes

  • Question 160:

    A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project.

    Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)

    A. Train users on the proper use of the system.

    B. Escalate the issue to the CCB.

    C. Hold sessions to understand user challenges.

    D. Track system usage and report user activity.

    E. Log the issue in the project risk register.

    F. Create a memorandum of acceptable use.

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-005 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.