  • Question 151:

    The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

    A. Cost performance index
    B. Risk mitigation
    C. Schedule variance
    D. Cost variance

  • Question 152:

    The difference between a risk matrix and a risk register is that:

    A. the risk register states the risk owner.
    B. the risk register contains less information than the risk matrix.
    C. the risk matrix states the risk owner.
    D. the risk matrix lists the risk description.

  • Question 153:

    Which of the following project plan components would include information regarding the management of issues?

    A. Project Management Plan
    B. Human Resources Plan
    C. Risk Management Plan
    D. Scope Management Plan

  • Question 154:

    Which of the following conflict resolution techniques involves one party overpowering another without regard to relationships within the group?

    A. Avoiding
    B. Smoothing
    C. Forcing
    D. Compromising

  • Question 155:

    Which of the following techniques is premised by a relatively small number of causes resulting in the majority of defects?

    A. Law of averages
    B. Six sigma
    C. Pareto analysis
    D. Ishikawa diagram

  • Question 156:

    A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users. In which of the following components of the project plan should this be documented?

    A. Scope statement
    B. Issues log
    C. WBS
    D. Change form

  • Question 157:

    In order to ensure higher commitment levels, estimates should be created, or approved by:

    A. The person doing the work
    B. The customer
    C. The project manager
    D. Key stakeholders

  • Question 158:

    A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?

    A. Communications Plan
    B. Risk Register
    C. Work Breakdown Structure
    D. Change Log

  • Question 159:

    Which of the following are included in a risk register? (Select TWO).

    A. Project risk responses
    B. Identified risks
    C. Major milestones
    D. Risk analysis tools
    E. Risk control board members

  • Question 160:

    Which of the following is used to provide a functional description of the efforts which are required in order to accomplish a task?

    A. Gantt chart
    B. PERT
    C. GERT
    D. WBS dictionary

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.