CompTIA PK0-003 Online Questions & Answers

  • Question 141:

    When performing quantitative risk analysis, which of the following should be produced?

    A. Control chart
    B. Decision tree
    C. Run chart
    D. Scatter diagram

  • Question 142:

    Which of the following human resource outputs would a project manager use to determine a team member's skills?

    A. Role
    B. Accountability
    C. Competency
    D. Responsibility

  • Question 143:

    The project manager is trying to determine what to present at a project kick-off meeting. Should a high- level project schedule be included?

    A. It depends. Some stakeholders are not technical enough to understand them.
    B. No. The project is likely to still be in the initiation phase which is too early for a project schedule.
    C. Yes. Project schedules are required to ensure that stakeholders are bound to the scope.
    D. Yes. High level project schedules are typically presented at a kick-off meeting.

  • Question 144:

    Which of the following conflict resolution techniques involves pushing a single viewpoint at the expense of others?

    A. Smoothing
    B. Forcing
    C. Confronting
    D. Avoiding

  • Question 145:

    The design activity of a project has the following cost attributes:

    PV = 100,000 EV = 20,000 AC = 90,000

    Based on this scenario, calculate the schedule variance.

    A. -80,000
    B. -70,000
    C. 10,000
    D. 120,000

  • Question 146:

    Which of the following can aid in the identification of the cause of the majority of the defects on a given project?

    A. Ishikawa diagrams
    B. Run charts
    C. Histograms
    D. Pareto charts

  • Question 147:

    During a conflict, which of the following resolution techniques describes forcing?

    A. Working out an agreement that is acceptable to both sides
    B. Not addressing the conflict
    C. One side making the other side do what they are told
    D. Focusing on common interests

  • Question 148:

    In which of the following project life cycle phases would one perform the first stakeholder's analysis?

    A. Initiation
    B. Controlling
    C. Planning
    D. Monitoring

  • Question 149:

    A project manager has been presented a set of documents containing why a project is needed, how it fits in with the company objectives, and the revenue that will be generated by the product. Which of the following has the project manager just received?

    A. A business case
    B. A charter
    C. Key project deliverables
    D. Project objectives

  • Question 150:

    The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?

    A. -$2,500
    B. $12,500
    C. 0.67
    D. 1.5

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PK0-003 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.