In the last year, all program phase gate reviews received excellent feedback and exceeded stakeholder expectations. Recently, the customer decides that there is no need to continue phase gate reviews. What should the program manager do next?
A. Ask the stakeholders what they want and proceed with their recommendations.You have completed a project for a client at his facility. The project has lasted for 18 months and you have generated many reports, plans, change request forms, and other documents about the project work. What should you do with the project documentation?
A. Give it to the client for his information.A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
A. Escalate the issue to the stakeholder's supervisorYour program is to construct a new condo building in Chicago. You and the project managers are working together to define the project assumptions about the program. Which one of the following is an example of an assumption for this program?
A. Deadlines for project milestonesA risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
A. Reactionary risksAn IT program manager is concerned that a program is not achieving its defined incremental benefits due to a lack of delivery by the business team. The IT team has several dependencies on the business team throughout the program. However, the business team does not report to the IT program manager, and only two business team resources with the appropriate skills are available to complete the required program tasks.
To address this issue, what should the IT program manager do next?
A. Schedule a meeting with the business team to discuss transferring the two business team resources to the IT team; update the program risk register to include risk mitigation steps.You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?
A. 59,340A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet. What activity should the program manager perform next?
A. Program delivery managementThe program sponsor requests a weekly performance report. The tools and techniques to monitor and control program performance include which of the following?
A. Program management performance variances, business criteria reweighting, root cause identification, and statistical sampling.A new program is comprised of four component projects. The program manager must assign project managers to each of the four projects. There are eight potential project managers to consider. What should the program manager do before assigning the project managers?
A. Determine budgetary constraints related to the project managers' salariesNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PGMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.