HOTSPOT
You are the production scheduler for a manufacturing company.
You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.

A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
An employee discovers an error after a time and attendance record is approved and transferred. The payroll transfer has not been run. However, the time has been posted against the production order.
You need to reverse the transferred registrations.
What happens to the production order time posting?
A. The Production Report as Finished journal is posted.A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management. The company requires employees to register time against each machine on the shop floor.
You must configure the system to allow employees to register time.
Which two configurations must be set up? Each correct answer represents part of the solution.
NOTE: Each correct selection is worth one point.
A. time registration workersDRAG DROP
A company uses multiple Dynamics 365 applications to track and repair equipment.
The company wants to improve its repair order process. Repair technicians frequently encounter unexpected issues daily.
The technicians must be empowered to address the issues and create new work orders by doing the following:
1. Provide step-by-step, just-in-time training for work order completion in the field by using videos and text.
2. Document work order creation in a single, printable document.
3. Report on the use of hands-on training.
You need to implement a solution forth requirements.
Which solution should you implement for each requirement? To answer, drag the appropriate solutions to the correct requirements. Each solution may be used once, more than once, or not at all.
You may need to drag the split bar between panes or scroll to view content.
Select and Place:

HOTSPOT
A lean manufacturing company is implementing Dynamics 365 Supply Chain Management.
The manufacturer subcontracts a part of the production process.
Items must support the subcontracting process.
The subcontracted cost must be included in production
You need to configure the production process to meet the subcontracting requirements.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

A company employs a distributed hybrid topology within its Dynamics 365 Supply Chain Management system and rents distribution warehouse space at a major U.S. port. The company requires an operational cloud scale unit for this distribution warehouse.
You must set up the operational cloud scale unit.
Which three types of transactions can be created within the warehouse? Each correct answer provides a complete solution.
NOTE: Each correct selection is worth one point.
A. Transfer order for goods to other company locationsYou need to set up the state control for sales of motorcycles.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A. Create an inclusive restricted product list for United States. Do not add the motorcycle part to the list.A company manufactures both generic and name-brand paper plates in the same facility using standard costing, sharing the same Bill of Materials (BOM) and routes for both products. The finance and production teams need a way to view the individual raw material consumption costs in the ledger.
You must add a production group to the finished goods to control postings to the ledger.
What actions should you take?
A. Update the cost of the generic nished good item.DRAG DROP
You need to configure the solution for the two issues the production manager reported.
How should you complete the configurations?
To answer, move the appropriate configurations to the correct issues. You may use each configuration once, more than once, or not at all. You may need to move the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Select and Place:

HOTSPOT
A candy manufacturer uses Dynamics 365 Supply Chain Management.
A master planning run needs to prioritize the production jobs for fruit snacks by flavor and color every 16 days.
You need to configure the appropriate parameters in the coverage group.
What should you configure? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your MB-335 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.