CompTIA JK0-017 Online Questions & Answers

  • Question 311:

    In regards to proper change management procedures, which of the following would be the FINAL activity?

    A. Coordinate with the appropriate stakeholders to determine course of action.
    B. Document the change using the appropriate change control forms.
    C. Perform impact analysis with project team members.
    D. Update the project plan components based on the approved change request.

  • Question 312:

    A project manager has an initial problem with a remote team members performance. Which of the following is the BEST form of communication to address this issue?

    A. Formal written communications
    B. Informal written communications
    C. Informal verbal communications
    D. Formal verbal communications

  • Question 313:

    The project manager has been informed that the project team cannot procure any more materials until a new purchase order has been received. The project manager should record this information in which of the following documents?

    A. Risk response plan
    B. Communications plan
    C. Issues log
    D. Change control log

  • Question 314:

    A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

    A. Staff
    B. Risk
    C. Cost
    D. Time

  • Question 315:

    A project manager has determined the probability and impact of identified project risks. A meeting with the project team will be held to determine how to mitigate risks above the project threshold. Which of the following will be created during this meeting?

    A. Risk response strategies
    B. Risk register
    C. Risk assessment
    D. Stakeholder risk tolerance

  • Question 316:

    A new project manager has been assigned to a high profile project. In order to determine project status, which of the following should the project manager do? (Select Two).

    A. Ask the key stakeholders for the project status.
    B. Leave a voicemail message to key personnel requesting the project status.
    C. Schedule a meeting with the team members to determine the project status.
    D. Send an email to the team members to request project status reports.
    E. Schedule a meeting with the project sponsor to determine the project status.

  • Question 317:

    The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?

    A. Create a modified version of the project schedule applying the critical path method.
    B. Call a project team meeting to use combined expert judgment to accept or reject the change request.
    C. Create a Pareto chart for the outputs from the specific work-packages identified by the change control board.
    D. Crash the schedule to meet the original deadlines.

  • Question 318:

    Which of the following activities would happen FIRST in procurement management?

    A. Request seller responses.
    B. Perform a make or buy analysis.
    C. Perform contract administration.
    D. Perform vendor selection.

  • Question 319:

    Which of the following would be included in a project scope document? (Select Two).

    A. Project constraints
    B. WBS dictionary
    C. Project assumptions
    D. Project charter
    E. Work Breakdown Structure (WBS)

  • Question 320:

    Which of the following is the correct formula for computing a projects SPI?

    A. SPI = EV - AC
    B. SPI = EV / PV
    C. SPI = EV - PV
    D. SPI = EV / AC

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only CompTIA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your JK0-017 exam preparations and CompTIA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.