You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach?
A. SequentialWhich of the followingis a factor that is likely to increase the test estimate? [1]
A. Use of a new technologyYou are a Test Manager at a company that develops mobile phone applications. Based on historical data in your company, you have calculated the following average metrics for system testing: for each 100 LOC (Lines Of Code). 4 test cases are executed each test case takes on average 15 minutes to execute and check for each 1000 LOC, 5 defects are found You have used this information to create an estimate for the system testing of a new mobile phone application being developed to submit gas and electricity readings. The application delivered for system testing has 50.000 lines of code. At the end of system testing, 250 defects are discovered. Assume that: the system test of the new mobile phone application will require the same amount of effort as previous applications defect density = number of defects/1000 LOC no new tools or processes have been introduced to the test team Based only on the given information, which one of the following statements is true about this new mobile phone application? SELECT ONE OPTION
A. The time taken to run all the estimated tests would be 750 hours.Which of the following describes the Failure Mode and Effect Analysis (FMEA) risk analysis technique? SELECT ONE OPTION
A. FMEA is a quality risk management technique concerned with quality risks that arise from an incorrect understanding of the customer requirements.Club 65 to 90 is a holiday club for retired people run by a small company, the IT department consists of 1 Designer, 3 Developers and 1 System Tester Their booking system has been "live" for a number of years and the company has a loyal
client base. A variety of automation tools are used for development and testing to improve effectiveness and efficiency.
A new project will introduce a loyalty scheme and both a Business Requirement Specification and a System Design Specification have been produced A Rapid Application Development (RAD) lifecycle model will be used where time is crucial.
In the past there have been problems with updates to the existing system, which has affected existing functionality. Testers have not used representative and realistic operational profiles and data, which has led to significant production
problems. The following test policy statements have been proposed for the project:
a- Testing must be risk based;
b- A Master Test Plan, confirming to IEEE829, must be produced for each test project;
c- Test procedures must be run by a tester who did not write the procedure;
d- Regression testing should be carried out on all releases;
e- The testers are accountable for all defects found in production;
f- Time must be given to designing test environments so that they are representative of the live environment.
Which of the following options identifies the three policy statements that would be MOST beneficial for this project?
A. a, d and e.Your company specialises in offering travel insurance policies to the over 60 age bracket. It is starting a new project to modernise the design of its website, which is seen to be inferior to its competitors. The project will use a SCRUM software
development methodology.
As senior test manager for your company, you have been asked to identify three test analysts to join the SCRUM development team. There are a number of testers currently not allocated to projects who would be available, all of them have
been with the company for a number of years, although some have little or no experience in iterative development.
You must assess their current skillsets to determine whether any of them possess skills that would be of particular relevance for the new project. Which TWO of the following skills should you focus on in your assessment?
A. Methodological competence - the ability to analyse the test basis and deal with product risksYour defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?
A. Defects that are projected but have not been found yetYou are writing the project test plan and are analysing the following risks in the project risk register:

Which would be the MOST appropriate test activities to mitigate the product risks?
A. Ignore Risk 1 as this cannot be mitigated by testing activities. Apply performance testing for Risk 2 and schedule it ahead of security testing for Risk 4. Disregard Risk 3 as it cannot be mitigated by test activitiesA car rental company offers discounts to its customers based on a number of factors, including booking history, length of membership and type of car being booked. An update to the rental application is under test, with test cases written that specifically address a documented product risk covering discount calculation. Although the risk impact was analysed as high, the likelihood was given as low, as there had been no known changes to the calculation rules. However, during test execution some discount calculations were incorrect and investigation showed that code changes had been made that impacted the discount algorithms. As a result, the likelihood was increased to high by the risk management team. Which would be the BEST measure to take to respond to the current situation?
A. Monitor the risk and adjust the risk register to reflect the changed risk level and any new risksdiscoveredYou are the manager of a test team. You inherited most of these people from a previous manager who promoted technical skills, particularly
programming skills. As a result, your people are very strong in test automation skills, white box testing and complex test design techniques. You have just been told that you can hire five new people. You want the new people to complement
the existing skill sets and you want to be sure the team will have a strong mutual respect.
Given the following options, who should you hire? [3]
A. Hire all black box testers because you are severely lacking in that skill set.Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISTQB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your ISTQB-CTAL-TM exam preparations and ISTQB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.