  • Question 201:

    Which of the following types of signatures is used in an Intrusion Detection System to trigger on attacks that attempt to reduce the level of a resource or system, or to cause it to crash?

    A. Access
    B. Benign
    C. DoS
    D. Reconnaissance

  • Question 202:

    You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

    A. Cause and effect diagrams
    B. Influence diagrams
    C. Predecessor and successor diagramming
    D. System or process flowcharts

  • Question 203:

    Which of the following statements about the integrity concept of information security management are true? Each correct answer represents a complete solution. Choose three.

    A. It ensures that unauthorized modifications are not made to data by authorized personnel or processes.
    B. It determines the actions and behaviors of a single individual within a system
    C. It ensures that internal information is consistent among all subentities and also consistent with the real-world, external situation.
    D. It ensures that modifications are not made to data by unauthorized personnel or processes.

  • Question 204:

    Which of the following programming languages are compiled into machine code and directly executed by the CPU of a computer system? Each correct answer represents a complete solution. Choose two.

    A. C
    B. Microosft.NET
    C. Java EE
    D. C++

  • Question 205:

    Which of the following is the most secure method of authentication?

    A. Biometrics
    B. Username and password
    C. Anonymous
    D. Smart card

  • Question 206:

    Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?

    A. Configuration management system
    B. Scope change control system
    C. Cost change control system
    D. Integrated change control

  • Question 207:

    Which of the following is an attack with IP fragments that cannot be reassembled?

    A. Password guessing attack
    B. Teardrop attack
    C. Dictionary attack
    D. Smurf attack

  • Question 208:

    In which of the following cryptographic attacking techniques does an attacker obtain encrypted messages that have been encrypted using the same encryption algorithm?

    A. Chosen plaintext attack
    B. Chosen ciphertext attack
    C. Ciphertext only attack
    D. Known plaintext attack

  • Question 209:

    Joseph works as a Software Developer for WebTech Inc. He wants to protect the algorithms and the techniques of programming that he uses in developing an application. Which of the following laws are used to protect a part of software?

    A. Code Security law
    B. Patent laws
    C. Trademark laws
    D. Copyright laws

  • Question 210:

    Bill is the project manager of the JKH Project. He and the project team have identified a risk event in the project with a high probability of occurrence and the risk event has a high cost impact on the project. Bill discusses the risk event with Virginia, the primary project customer, and she decides that the requirements surrounding the risk event should be removed from the project. The removal of the requirements does affect the project scope, but it can release the project from the high risk exposure. What risk response has been enacted in this project?

    A. Mitigation
    B. Transference
    C. Acceptance
    D. Avoidance

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CSSLP exam preparations and ISC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.