is a usual process to start with the due date and using find lead time, to work back to operations?
A. Efficiency
B. Utilization
C. Back Scheduling
D. Capacity management
1.
Determine the standard hours of operation time for each planned and released order for each work center by time period.
2.
Add all the standard hours together for each work center in each period. These are the steps of calculating:
A. load
B. Capacity required
C. Available capacity
D. None of these
In the previous problem how much actual time will be needed to run the order if the work center has an efficiency of 120% and a utilization of 80%?
A. 38 hours
B. 38.2 hours
C. 32.8 hours
D. 32 hours
A work center is to process 150 units of gear shaft SG 123 on work order 333.the setup time is 1.5 hours, and the run time is 0.2 hours per piece. What is the standard time needed or run the order?
A. 31.5 standard hours
B. 30 standard hours
C. 29.5 standard hours
D. 28 standard hours
is a two-step process. First determine the time needed for each order at each order at each work center. Then sum up the capacity required for individual orders?
A. Load
B. Capacity required
C. Available capacity
D. Both A and B are same
Over a 4-week period a work center produced 540 standard hours of work was available for 640 hours, and actually worked 480 hours. Calculate the utilization and the efficiency of the work center.
A. 75%, 110%
B. 75%, 112.9%
C. 76%, 112.95%
D. 75%, 110%
Demonstrated capacity is:
A. Minimum output
B. Average Output
C. Maximum output
D. None of these
Over the previous four weeks, a work center produced 120, 130, 150,140 standard hours of work. What is the demonstrated capacity of the work center?
A. 135 standard hours
B. 139 standard hours
C. 140 standard hours
D. 130 standard hours
One way to find out the capacity of a work center is to examine the information as the available capacity of the work center.
A. Production records
B. Available inventory
C. Utilization
D. Efficiency
A work center produces 120 units in a shift. The standard for that item is units a shift. What is 100 the efficiency of work center?
A. 120%
B. 20%
C. 100%
D. 80%
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.