Exam Details

  • Exam Code
    :CPIM-MPR
  • Exam Name
    :CIPM - Master Planning of Resources
  • Certification
    :APICS Certifications
  • Vendor
    :APICS
  • Total Questions
    :588 Q&As
  • Last Updated
    :Jul 11, 2025

APICS APICS Certifications CPIM-MPR Questions & Answers

  • Question 341:

    Repetitive Manufacturing and continuous manufacturing are types of:

    A. Flow Manufacturing

    B. Intermittent Manufacturing

    C. Project Manufacturing

    D. None of these

  • Question 342:

    Manufacturing process can be conveniently organized into following categories EXCEPT:

    A. Flow Manufacturing

    B. Intermittent Manufacturing

    C. Project Manufacturing

    D. Work Center Manufacturing

  • Question 343:

    Which one of the following is NOT done by PAC in control phase?

    A. Monitor and control work-in-process, lead times, and work center queues.

    B. Report work center efficiency, operation times, order quantities and scrap.

    C. Track the actual performance of work orders and compare it to planned schedules.

    D. Ensure that required materials, tooling, personnel and information are available.

  • Question 344:

    This is a true representation

    A. MRP

    B. Capacity Control

    C. PAC

    D. MRP II

  • Question 345:

    Gather the information needed by the shop floor to make the product. Release orders to the shop floor as authorized by the material equipment plan. This is called dispatching. Production activity control will do such things in:

    A. Planning phase

    B. Implementation phase

    C. Control phase

    D. Both A and B

  • Question 346:

    The flow of work centers must be planned to meet delivery dates which means production activity control must do the following:

    A. Ensure that the required materials, tooling, personnel and information are available to manufacture the components when needed.

    B. Schedule start and completion dates for each shop order at each work center so the scheduled completion date of the order can be met. This sill involves a planner in developing a load profile for the work centers.

    C. Both of these

    D. None of these

  • Question 347:

    The material requirement plan authorizes production activity control (PAC):

    A. To work orders to the shop for manufacturing

    B. To take control of work orders and make sure they are completed on time

    C. To manage day-to-day activity and provide the necessary support

    D. All of these

  • Question 348:

    Production activity control is responsible for executing the:

    A. Production Schedule

    B. MRP

    C. Both of these

    D. Capacity control

  • Question 349:

    How many standard hours are needed to run an order of 200 pieces if the setup time is 1.3 hours and the run time 0.3 hours per piece? How many actual hours are needed at the work center if the efficiency.130% and the utilization is 70%?

    A. 51.3 standard hours; 67.4 actual hours

    B. 62 standard hours; 60.4 actual hours

    C. 61.3 standard hours; 67.4 actual hours

    D. 61.3 standard hours; 60.4 actual hours

  • Question 350:

    Over a period of 4 weeks, a work center produced 50, 45, 40, and standard house of work. What is the demonstrated capacity of the work center?

    A. 47.8

    B. 47.5

    C. 48

    D. 49.5

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.