Material Requirements Planning (MRP) is:
A. The system used to provide available inventory
B. The system used to avoid missing parts.
C. A schedule establish for the production agenda
D. All of the above
A schedule (priority plan) that establishes to show the components required at each level of the assembly and based on lead time, calculates the time when these component will be needed called:
A. Material Requirements Planning
B. Master Production Schedule
C. Inventory control Planning
D. B and C
For each product how the product is made.
A. Routing file
B. Work-center master file
C. Control file
D. Shop-order master file
The product structure file:
A. Contains a list of single-level components and quantities needed to assemble
B. Forms a basis fro a parent pick list.
C. Both of these
D. None of these
Planning file/s needed for the production activity control is/are:
A. Item master file
B. Product structure file
C. Routing and work center master file.
D. All of these
To plan the processing of materials through manufacturing PAC must have the following information EXCEPT:
A. What and how much to produce
B. When parts are needed so the completion date can be met.
C. What are scheduled receipts for various orders
D. What the available capacities of various work centers are
Production activity control in intermittent manufacturing is complex Because of:
A. The number of products made
B. The variety of routing
C. Scheduling problems
D. All of the above
1.
Flow of work through the shop is varied and depends on the design of a particular product. As orders are processed, they will take more time at once workstation than at another. Thus, the work flow is not balanced.
2.
Machinery and workers must be flexible enough to do the variety of work. Machinery and work centers are usually grouped according to the function they perform (e.g. all lathes in one department).
3.
Throughput times are generally long. Scheduling work to arrive just when needed is difficult, the time taken by an order at each work center varies, and work queues before work centers, causing long delays in processing. Work-in-process inventory is often large.
4.
The capacity required depends on the particular mix of products being built and is difficult to predict.
These are the characteristics of:
A. Flow manufacturing
B. Project manufacturing
C. Intermittent manufacturing
D. All of these
is characterized by many variations in product design, process requirements and order quantities.
A. Flow manufacturing
B. Project manufacturing
C. Intermittent manufacturing
D. None of these
Which of the following is/are the major characteristic/s to flow manufacturing?
A. Routing are fixed and work centers are arranged according to the routing.
B. Work centers are dedicated to producing a limited range of similar products.
C. Material flows from one workstation to another.
D. All of these
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.