APICS CPIM-MPR Online Questions & Answers

  • Question 131:

    Strategic business plans are usually reviewed

    A. After each quarter
    B. Every six months to a year
    C. After five years
    D. Both A and B

  • Question 132:

    The time needed to unload and load must be shorter than .

    A. run time per piece
    B. planning time
    C. manufacturing time
    D. resource utilization time

  • Question 133:

    The time needed to perform operation is an important input factor to the manufacturing planning

    and control system. It is needed to schedule work through the plans,

    A. Load the plant
    B. Make delivery promises
    C. And cost the product
    D. All of these

  • Question 134:

    What the following figure shows:

    A. The parent omponent relationship
    B. Quantity and parts relationship
    C. Identification of the parts
    D. None of the above

  • Question 135:

    Where-used reports give information about

    A. The parents for a component
    B. Independent and dependent demand
    C. Both A and B
    D. None of the above

  • Question 136:

    Basic strategies that can be used in a production plan may be:

    A. Chase strategy
    B. Production leveling strategy
    C. Subcontracting
    D. Any one of these

  • Question 137:

    A convenient way to think about bills of material is through:

    A. Product Tree
    B. Dependent demand
    C. Inventory record
    D. All of the above

  • Question 138:

    Planned input 30 30 20 20 20 20 Planned output 20 20 20 20 20 20 Planned backlog Actual backlog 50 The planned backlog at the end of period 6 is?

    A. 70
    B. 65
    C. 60
    D. 50

  • Question 139:

    is a two-step process. First determine the time needed for each order at each order at each work center. Then sum up the capacity required for individual orders?

    A. Load
    B. Capacity required
    C. Available capacity
    D. Both A and B are same

  • Question 140:

    Customer requirements may be based on price, quality, delivery and so forth are called:

    A. Order qualifiers
    B. Order prerequisites
    C. Order basis
    D. None of these

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM-MPR exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.