What plan includes the description of the scope of work, the deliverable Work Breakdown Structure, the activity list, and estimates for the business analysis activities?
A. Project management planA project is implemented using a predictive approach. Unfortunately, a lot of change requests (CR) have been raised. A project manager (PM), who should approve each change request, is overworked. What could the business analyst (BA) propose to make things better?
A. Approve the CRs independently for the PMThe business analyst (BA) has been tasked with assessing and recommending the best solution that fits an organization's need for a new third-party sales tool.
What technique would be used for identifying suitable options?
A. Balanced scorecardA business analyst (BA) has just completed a number of elicitation activities and is preparing to review the stated requirements. As part of this, the BA is checking the compliance of the stated requirements with organizational standards for business analysis.
What state is the BA attempting to move the requirements into?
A. ValidatedA large insurance company wants to buy a new claims processing system or upgrade one of its two existing systems. Each year the claims department is given a $3,5 million budget to spend. Time is of the essence since there are some
regulatory changes that will be coming the following year that will require several features that currently neither one of the two claims systems currently support.
There are eight stakeholders involved in this initiative. There are local to where the claim systems are managed, while five are located across the country. The business analyst (BA) struggled to get all stakeholders to agree on the desired
features but ultimately got agreement on ten identified key features for the new claims systems. The BA was able to build a current state and future state process model which included all ten key features.
System A processes 75% of the company's claims. It is 5 years old and the claim processors love it because it is easy to use. However it must go offline for two hours each day. The code is very modular so it does have flexibility to be
modified. To upgrade system A to have all ten features it would cost %5 million. System A would be at capacity if it were to process all of the company's claims.
System B processes 25% of the company's claims. It is an older mainframe system, but rarely goes offline. It could easily handle double the number of claims that system A processes. However, it has a lot of legacy code and would cost $6
million to upgrade.
Both systems have some of the ten desired key features. But neither system has all ten. The cost to buy a new system would be $7 million.
Below is the estimated cost for each feature in priority order.

If the budget for the initiative was firm, what is a feasible solution to make sure the project stays within budget?
A. Upgrade system B with the first 8 featuresYou are the business analyst for your organization and management has asked that you identify opportunities to improve the operations of the business. You notice that some of the stakeholders use several pieces of software and several duplicate activities within each software package to generate data reports for customers.
What type of recommendation can you make in regard to this observation?
A. You can address the automation of how the workers perform.During a retrospective, the project team agrees the way they organized the user stories during the first sprint could be improved. The business analyst (BA) plans to make the stories more accessible going forward. Which of the following will the BA update?
A. Organizational performance standardsYou are the business analyst for your organization and are coaching Roberta on how business analysis works. Roberta is confused about what a business analysis methodology is during the business analysis planning and monitoring phase of the business analysis duties.
What is a methodology?
A. A methodology is a formalized and repeatable business analysis approach.Mark is the business analyst for his organization. Mark and his business analysis team have used the whiteboard to record the documentation as the result of requirements elicitation.
What must be done with this information if Mark uses a whiteboard?
A. The scribe must include the white board information as part of the minutes.All of the following are techniques that can be used to specify or model requirements except for which one?
A. Organization modelingNowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only IIBA exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CBAP exam preparations and IIBA certification application, do not hesitate to visit our Vcedump.com to find your solutions here.