  • Question 851:

    Within a matrix organization, dual reporting of team members is a risk for project success. Who is responsible for managing this dual reporting relationship factor?

    A. Functional manager
    B. Project manager
    C. Functional manager supported by the project manager
    D. Project management office

  • Question 852:

    How does planning for prevention costs assist in meeting stakeholder needs and expectations, while still providing required performance and reliability?

    A. It details product or service failures experienced by the customer
    B. It clarifies the costs associated with assessing the quality of the product or service
    C. It accounts for costs used to avoid poor quality in the product or service
    D. It communicates product or service failures discovered by the project team

  • Question 853:

    A project manager builds consensus and overcomes obstacles by employing which communication technique?

    A. Listening
    B. Facilitation
    C. Meeting management
    D. Presentation

  • Question 854:

    Which of the following methods is a project selection technique?

    A. Flowcharting
    B. Earned value
    C. Cost-benefit analysis
    D. Pareto analysis

  • Question 855:

    A project manager is performing a specific process and has a list of accepted deliverables. One of the stakeholders points out that they have just reviewed the verified deliverables, and come up with the list of accepted deliverables. Which process is being referred to?

    A. Control Quality
    B. Validate Scope
    C. Validate Quality
    D. Control Scope

  • Question 856:

    What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

    A. 0.03
    B. 0.06
    C. 0.10
    D. 0.50

  • Question 857:

    Projects can intersect with an organization's operations at various points during the product life cycle such as:

    A. When there is an operations shutdown (i.e. a strike).
    B. When developing new products, upgrading products, or expanding outputs.
    C. When a project transitions from a temporary to a permanent status.
    D. When the project manager is promoted to operations manager.

  • Question 858:

    An input to the Manage Project Team process is:

    A. Work performance reports.
    B. Change requests.
    C. Activity resource requirements.
    D. Enterprise environmental factors.

  • Question 859:

    A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified.

    How many communication channels are available?

    A. 8
    B. 18
    C. 36
    D. 40

  • Question 860:

    Which component of the project charter defines what the project's success will look like?

    A. Project objective
    B. Project approval requirements
    C. Project exit criteria
    D. High-level requirements

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.