  • Question 841:

    Which is an example of a technical project management skill?

    A. Managing a project schedule
    B. Developing a project delivery strategy
    C. Establishing a project team
    D. Understanding organizational objectives

  • Question 842:

    Stakeholder communication requirements should be included as a component of:

    A. enterprise environmental factors
    B. organizational process assets
    C. the project management plan
    D. the stakeholder register

  • Question 843:

    Which of the following are three inputs to the risk register?

    A. Risk register updates, stakeholder register, and quality management plan
    B. Communication management plan, enterprise environmental factors, and activity duration estimates
    C. Risk management plan, activity cost estimates, and project documents
    D. Project scope statement, organizational process assets, and scope baseline

  • Question 844:

    Which project manager competency is displayed through the knowledge, skills, and behaviors related to specific domains of project, program, and portfolio management?

    A. Leadership management
    B. Technical project management
    C. Strategic management
    D. Business management

  • Question 845:

    Which input will be used when tasked with developing the human resource plan?

    A. Project management plan
    B. Activity resource requirements
    C. Resource calendar
    D. Project staff assignments

  • Question 846:

    Risk exists the moment that a project is:

    A. planned.
    B. conceived.
    C. chartered.
    D. executed.

  • Question 847:

    Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

    A. Project sponsor and project manager
    B. Project sponsor and functional manager
    C. Project manager and project team
    D. Project team and functional manager

  • Question 848:

    An associate who calculates fees daily to support the department is doing which of the following?

    A. Phase work
    B. Project work
    C. Lifecycle work
    D. Operations work

  • Question 849:

    A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?

    A. Approved change requests
    B. Verified deliverables
    C. Lessons learned
    D. Work performance data

  • Question 850:

    A team was hired to develop a next generation drone. The team created a prototype and sent it to the customer for testing. The feedback collected was used to refine the requirements. What technique is the team using?

    A. Early requirements gathering
    B. Feedback analysis
    C. Progressive elaboration
    D. Requirements documentation

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.