PMI CAPM Online Questions & Answers

  • Question 861:

    Which three techniques can be estimate costs?

    A. Financing, bottom-up estimating, and expert judgment
    B. Cost aggregation, analogous estimating, and financing
    C. Expert judgment, financing, and cost aggregation
    D. Expert judgment, analogous estimating, and bottom-up estimating

  • Question 862:

    What is the total float of the critical path?

    A. Can be any number
    B. Zero or positive
    C. Zero or negative
    D. Depends on the calendar

  • Question 863:

    In an adaptive or agile life cycle, how are the customer and sponsor involved in the project scope management activities?

    A. Involvement is needed only during project initiation
    B. Minimal involvement of stakeholders is sufficient
    C. They should be continuously engaged
    D. They should be involved only during phase or deliverable reviews

  • Question 864:

    The handoff of the first version of a software application to the operational team has taken a month longer than anticipated.

    How could this extended transition time have been avoided?

    A. If the transition process was agreed upon during the build
    B. If the end-user documentation was more thorough
    C. If the operation team members were trained externally
    D. If the operations manager was invited to all sprint reviews

  • Question 865:

    Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

    A. Compromising
    B. Collaborating
    C. Smoothing
    D. Problem Solving

  • Question 866:

    Which of the following is a tool and technique for Estimate Activity Durations?

    A. Parametric estimating
    B. Monte Carlo analysis
    C. Alternatives analysis
    D. Bottom-up estimating

  • Question 867:

    Which of the following tools and techniques is used to estimate cost?

    A. Budget forecast
    B. Variance analysis
    C. Activity cost estimate
    D. Three-point estimate

  • Question 868:

    What risk response strategy involves removing high-risk scope elements from a project?

    A. Transfer
    B. Avoid
    C. Exploit
    D. Accept

  • Question 869:

    Which of the following correctly lists the configuration management activities included in the Integrated Change Control process?

    A. Configuration definition, configuration status accounting, configuration monitoring and control
    B. Configuration identification, configuration status accounting, configuration verification and audit
    C. Configuration identification, configuration status reporting, configuration verification and audit
    D. Configuration definition, configuration status reporting, configuration monitoring and Control

  • Question 870:

    Verification of project deliverables occurs during which process?

    A. Develop preliminary project scope statement
    B. Close Project or Phase
    C. Develop project charter
    D. Create WBS

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.