CAPM Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (CAPM)
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :1470 Q&As
  • Last Updated
    :May 28, 2026

PMI CAPM Online Questions & Answers

  • Question 721:

    Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

    A. Perform Qualitative Risk Analysis
    B. Perform Quantitative Risk Analysis
    C. Plan Risk Management D. Plan Risk Responses

  • Question 722:

    What are the four management processes included in the Project Cost Management (PCM) method?

    A. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
    B. Control Costs, Project Cost Management, Determine Budget, Estimate Costs
    C. Estimate Activities, Control Costs, Project Cost Management, Determine Budget
    D. Control Quality, Project Cost Management, Estimate Costs, Determine Budget

  • Question 723:

    Which of the following is an output of the Perform Integrated Change Control process?

    A. Project document updates
    B. Organizational process assets updates
    C. Change requests
    D. Deliverables

  • Question 724:

    While working in an adaptive environment, a business analyst is collaborating with other roles in drafting a product roadmap.

    Which three roles are involved in establishing the product roadmap? (Choose three.)

    A. End user
    B. Program manager
    C. Portfolio manager
    D. Project sponsor
    E. Internal inspector

  • Question 725:

    In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

    A. Start-to-start (SS)
    B. Start-to-finish (SF)
    C. Finish-to-finish (FF)
    D. Finish-to-start (FS)

  • Question 726:

    When the business objectives of an organization change, project goals need to be:

    A. realigned.
    B. performed.
    C. improved.
    D. controlled.

  • Question 727:

    The project manager is looking at a precedence diagram and needs to report back about the project status The total duration of the task is ten days, and both Activity A and B need be completed. Activity A has a duration of six days, and activity B has a duration of four days Activity B has a finish-to-start relationship with activity A Under current circumstances, activity A will take about seven days to complete.

    What is the outcome of the duration of this task'?

    A. The task will be completed on time.
    B. The task will not be completed on time.
    C. Activity A is not a critical path task
    D. The precedence diagram cannot be used to provide answers for duration calculations

  • Question 728:

    Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

    A. The Delphi technique
    B. Nominal group technique
    C. Affinity diagram
    D. Brainstorming

  • Question 729:

    A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

    A. triangular distribution
    B. tornado diagram
    C. beta distribution
    D. fishbone diagram

  • Question 730:

    Which document can help a project manager to leverage historical project information?

    A. Lessons learned register
    B. Schedule baseline
    C. Work performance data
    D. Deliverable acceptance forms

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.