PMI CAPM Online Questions & Answers

  • Question 711:

    Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

    A. Bottom-up
    B. Parametric
    C. Analogous
    D. Three-point

  • Question 712:

    What are the requirements that describe the behaviors of a product called?

    A. Functional requirements
    B. Nonfunctional requirements
    C. Solution requirements
    D. Transition requirements

  • Question 713:

    The scope management plan and scope baseline are contained in:

    A. organizational process assets
    B. a requirements traceability matrix
    C. the project charter
    D. the project management plan

  • Question 714:

    The Perform Quality Assurance process occurs in which Process Group?

    A. Executing
    B. Monitoring and Controlling
    C. Initiating
    D. Planning

  • Question 715:

    A risk may be graded into different priorities by which process?

    A. Risk monitoring and controlling
    B. Risk response planning
    C. Qualitative risk analysis
    D. Quantitative risk analysis

  • Question 716:

    Technical capability, past performance, and intellectual property rights are examples of:

    A. performance measurement criteria
    B. source selection criteria
    C. product acceptance criteria
    D. phase exit criteria

  • Question 717:

    A subject matter expert (SME) was recently assigned to a project to manage the new compliance requirement. The SME claimed that the activity's prioritization needed to change and the schedule could be cut to mitigate the effect of this new compliance need.

    How should the project manager proceed?

    A. Perform Integrated Change Control.
    B. Update the schedule to include compliance.
    C. Manage Stakeholder Engagement.
    D. Conduct a risk assessment with the team.

  • Question 718:

    The diagram below is an example of a:

    A. Risk breakdown structure (RBS).
    B. Project team.
    C. SWOT Analysis.
    D. Work breakdown structure (WBS).

  • Question 719:

    Who is responsible for the business case development document?

    A. Project manager
    B. Project stakeholders
    C. Project team
    D. Project sponsor

  • Question 720:

    The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

    A. Work packages.
    B. Accepted deliverables.
    C. The WBS dictionary.
    D. The scope baseline.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.