PMI CAPM Online Questions & Answers

  • Question 691:

    Project Stakeholder Management focuses on: A. project staff assignments

    B. project team acquisition
    C. managing conflicting interests
    D. communication methods

  • Question 692:

    What is a tailoring consideration for the application of Project Risk Management processes?

    A. Project complexity
    B. Procurement criteria
    C. Communication technology
    D. Knowledge management

  • Question 693:

    What process is performed periodically throughout the project as needed?

    A. Plan Risk Management
    B. Plan Communications Management
    C. Plan Resource Management
    D. Plan Cost Management

  • Question 694:

    Which of the following is a strategy to deal with positive risks or opportunities?

    A. Mitigate
    B. Transfer
    C. Exploit
    D. Avoid

  • Question 695:

    Who selects the appropriate processes for a project?

    A. Project stakeholders
    B. Project sponsor and project stakeholder
    C. Project manager and project team
    D. Project manager and project sponsor

  • Question 696:

    Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?

    A. Sponsors
    B. Project team
    C. Steering committees
    D. Stakeholders

  • Question 697:

    Which of the following factors is lowest at the start of the project?

    A. Cost of changes
    B. Stakeholder influences
    C. Risk
    D. Uncertainty

  • Question 698:

    The business needs, assumptions, and constraints and the understanding of the customers' needs and high-level requirements are documented in the:

    A. Project management plan.
    B. Project charter.
    C. Work breakdown structure.
    D. Stakeholder register.

  • Question 699:

    In which Project Cost Management process is work performance data included?

    A. Plan Cost Management
    B. Estimate Costs
    C. Determine Budget
    D. Control Costs

  • Question 700:

    Which type of analysis is used as a general management technique within the Plan Procurements process?

    A. Risk assessment analysis
    B. Make or buy analysis
    C. Contract value analysis
    D. Cost impact analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.