PMI CAPM Online Questions & Answers

  • Question 611:

    Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

    A. Control charts
    B. Pareto diagrams
    C. Ishikawa diagrams
    D. Checksheets

  • Question 612:

    Which process requires implementation of approved changes?

    A. Direct and Manage Project Execution
    B. Monitor and Control Project Work
    C. Perform Integrated Change Control
    D. Close Project or Phase

  • Question 613:

    Which is the appropriate tool to identify the possible correlation between two elements in a process?

    A. Scatter diagram
    B. Cause-and-effect diagram
    C. Histogram
    D. Control charts

  • Question 614:

    Which of the following are processes associated with Project Cost Management?

    A. Develop Costs, Estimate Costs, Determine Budget, Control Costs
    B. Develop Budget, Determine Budget, Determine Risks, Control Costs
    C. Plan Cost Management, Estimate Costs, Determine Budget, Control Costs
    D. Plan Budget Management, Determine Budget, Create Cost Accounts, Control Costs

  • Question 615:

    For a stakeholder with low interest and high power, the project manager should:

    A. Monitor the stakeholder.
    B. Manage the stakeholder closely.
    C. Keep the stakeholder satisfied.
    D. Keep the stakeholder informed.

  • Question 616:

    Which of the following is the correct network diagram for the table?

    A. Begin-A-C-D-E-End-B-D
    B. Begin-A-B-C-D-E-End
    C. Begin-A-B-D-E-End A-C-D
    D. Begin-A-C-D-E-End-B-C

  • Question 617:

    Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

    A. Monitoring and Controlling
    B. Initiating
    C. Planning
    D. Executing

  • Question 618:

    Decomposition, rolling wave planning, and templates are all tools and techniques for which of the following?

    A. Define Activities
    B. Estimate Activity Durations
    C. Develop Schedule
    D. Sequence Activities

  • Question 619:

    During which process does the project team receive bids and proposals?

    A. Conduct Procurements
    B. Plan Procurements
    C. Estimate Costs
    D. Control Budget

  • Question 620:

    Which of the following items is a technique for data gathering?

    A. Facilitation
    B. Meeting management
    C. Conflict management
    D. Interviews

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.