PMI CAPM Online Questions & Answers

  • Question 601:

    Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

    A. Monitor and Control Risks
    B. Plan Risk Management
    C. Perform Qualitative Risk Analysis
    D. Perform Quantitative Risk Analysis

  • Question 602:

    The document that guides project execution, monitoring and control, and closure is called:

    A. The project charter
    B. The project management plan
    C. The integration plan
    D. The execution plan

  • Question 603:

    What process in Project Schedule Management identifies and documents specific actions to be performed to produce a project's deliverables?

    A. Plan Schedule Management
    B. Define Activities
    C. Develop Schedule
    D. Estimate Activity Durations

  • Question 604:

    Which tool or technique is an examination of industry and specific vendor capabilities?

    A. Independent estimates
    B. Market research
    C. Analytical techniques
    D. Bidder conferences

  • Question 605:

    The Process Group in which the internal and external stakeholders interact and influence the overall outcome of the project is the:

    A. Monitoring and Controlling Process Group.
    B. Initiating Process Group.
    C. Planning Process Group.
    D. Executing Process Group.

  • Question 606:

    Who is responsible for developing the project management plan and all related component plans?

    A. Project team
    B. Portfolio manager
    C. Project manager
    D. Project management office

  • Question 607:

    Perform Quantitative Risk Analysis focuses on:

    A. compiling a list of known risks and preparing responses to them
    B. assessing the probability of occurrence and impact for every risk in the risk register
    C. evaluating the contingency and management reserves required for the project
    D. analyzing numerically the impact of individual risks on the overall project's time and cost objectives

  • Question 608:

    In which Knowledge Area is the project charter developed?

    A. Project Cost Management
    B. Project Scope Management
    C. Project Time Management
    D. Project Integration Management

  • Question 609:

    Which of the following are inputs for the Plan Quality Management processes?

    A. Quality metrics, project documents, and financial performance
    B. Quality management plan, project documents, and quality metrics
    C. Project management plan, project documents, and organizational process assets
    D. Project management plan, quality metrics, and project documents

  • Question 610:

    Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?

    A. Bottom-up
    B. Three-point
    C. Parametric
    D. Analogous

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.