BICSI BICSI-RCDD Online Questions & Answers

  • Question 351:

    Which of the following serves as a guiding principle for a program manager

    when preparing a program work breakdown structure?

    A. Decompose the program work based upon available resources
    B. Decompose the program to the work package level
    C. Decompose the program lo the architecture baseline level
    D. Decompose the program at a level sufficient to achieve control

  • Question 352:

    Which two of the following are means

    in which radiated interference primarily enters electronic devices?

    (Select two options.)

    A. Proximity to interfering sources
    B. Missing or inadequate optical connections
    C. Missing or inadequate device or cable shielding
    D. Interface designs
    E. Input signal lines

  • Question 353:

    In a joint use trench,

    what is the minimum separation of telecommunication cables and power conduits in well-tamped earth?

    A. 3 feet
    B. 12 inches
    C. 6 inches
    D. 3 inches
    E. 4 inches

  • Question 354:

    The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.

    In this situation,

    what should the program manager change about the risk management plan?

    A. Allow the component project manager to delegate risk management responsibilities
    B. Assign the resolution of project-level risks to the component project manager
    C. Include risk escalation policies and procedures in the risk response plan
    D. Increase flexibility with risks that require a risk response

  • Question 355:

    An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)

    A. 0.006 m2 (8 in2)
    B. 0.008 m2 (12 in2)
    C. 0.040 m2 (60 in3)
    D. 0.60 m2 (80 in3)

  • Question 356:

    Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?

    A. Isolating transformers
    B. Neutralizing transformers
    C. Mutual drainage reactors
    D. Unit-type neutralizing transformers
    E. 2-winding neutralizing transformers

  • Question 357:

    Which two of the following are included in the ICT distribution designer's role of vendor and contractor coordination'? (Select two options.)

    A. Conduct final ICT inspections to ensure standard and code compliance, design intent, and/or client requirements are met.
    B. Monitor project schedule for delays
    C. Produce ICT closeout documentation for the owner to provide the record documentation of the installation
    D. Communicate status to stakeholders
    E. Assist in the resolution of unforeseen conditions, change orders. RFIs, and changes to the project's critical path

  • Question 358:

    An R&D group director approves a major program's charter although the director has a high level of understanding of the program's scope (hoy are unsure of how the program manager can be successful in delivering the program's commitments

    What should the program manager do to align stakeholders with planning and monitoring the program's progress?

    A. Establish high-level program milestones
    B. Develop an accountability matrix, and assign program roles and responsibilities
    C. Generate a supplier management plan to identify external stakeholders
    D. Create a communications management plan, and establish reporting formats

  • Question 359:

    Which of the following is the international standard for premises cabling?

    A. ISO/IEC 18010
    B. ISO/IEC 11801

  • Question 360:

    How does a portfolio's collection of work differ from that of a program's collection of work?

    A. Outcomes are interdependent
    B. Benefits are achieved only when managed collectively
    C. Components may be independent
    D. Outcomes are time bound

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only BICSI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your BICSI-RCDD exam preparations and BICSI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.