  • Question 51:

    In which product would you find a product's quality tolerance defined?

    A. Product Description

    B. Quality Management Strategy

    C. Quality Register

    D. Configuration Item Record

  • Question 52:

    Which is NOT a true statement about the Managing a Stage Boundary process?

    A. It provides sufficient information for the Project Board to review the success of the current stage

    B. It is used to create an Exception Plan if requested by the Project Board

    C. It provides a fixed point at which acceptance of the project product is confirmed

    D. It is executed at, or close to, the end of each management stage, except the final one

  • Question 53:

    Which is NOT one of the levels of plan recommended by PRINCE2?

    A. Benefits Review Plan

    B. Project Plan

    C. Stage Plan

    D. Team Plan

  • Question 54:

    Which is a purpose of a Lessons Log?

    A. Note any lessons that are raised in Checkpoint Reports

    B. Record that corrective action is being taken

    C. Escalate lessons to the Project Board

    D. Raise improvements with Project Assurance

  • Question 55:

    What theme estimates the cost of delivering the project?

    A. Business Case

    B. Change

    C. Plans

    D. Progress

  • Question 56:

    Which of the following are typical core activities within configuration management?

    1.

    Planning

    2.

    Risk assessment

    3.

    Verification and audit

    4.

    Identification

    A. 1, 2, 3

    B. 1, 2, 4

    C. 1, 3 ,4

    D. 2, 3, 4

  • Question 57:

    Why would the Project Manager escalate an issue to the Project Board?

    A. The Project Board is responsible for determining the priority of all issues

    B. Direction is required on the best response for preventing the issue from occurring

    C. The issue is forecast to cause a deviation beyond stage tolerance and advice is required

    D. Escalating issues is a means of providing the Project Board with a regular update on their status

  • Question 58:

    Which is a purpose of the Directing a Project process?

    A. Create and authorize the project mandate

    B. Ensure that work on products allocated to the team is authorized and agreed

    C. Control the day-to-day running of the project

    D. Delegate day-to-day management of the project to the Project Manager

  • Question 59:

    What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

    A. Configuration Item Record

    B. Quality Register

    C. Highlight Report

    D. Checkpoint Report

  • Question 60:

    Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans

    A. define a coding system to provide a unique identifier for the products within

    B. summarize the results of the quality activities performed on

    C. provide a framework to design, develop and maintain

    D. define the project benefits to be achieved by each of

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.