  • Question 1:

    Whose approval is needed to replace a Stage Plan with an Exception Plan?

    A. Corporate or programme management

    B. Project Board

    C. Project Manager

    D. Team Manager

  • Question 2:

    Which is a recommended quality review team role?

    A. Project Manager

    B. Assurance

    C. Project Support

    D. Administrator

  • Question 3:

    Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.

    A. Project Assurance

    B. Project Support

    C. the risk actionee

    D. the risk owner

  • Question 4:

    Which is a purpose of an End Project Report?

    A. Identify individuals or groups that need to be told that the project is coming to an end

    B. Review how well the project performed against the Project Initiation Documentation used to authorize it

    C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

    D. Ensure that key project information is archived and made secure

  • Question 5:

    Which is a purpose of the Starting up a Project process?

    A. Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate

    B. Define the means of communication between the project and corporate or programme management

    C. Define the project controls

    D. Record any identified risks in the Risk Register

  • Question 6:

    Which is a FALSE statement about technical stages?

    A. Can overlap with other technical stages

    B. Typified by the use a particular set of specialist skills

    C. Include the Managing a Stage Boundary process activities

    D. Can span more than one management stage

  • Question 7:

    Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

    A. Only corporate or programme management

    B. Only the Project Board

    C. Only the Project Manager

    D. All levels of management

  • Question 8:

    Which is a purpose of the Risk Register?

    A. Describe the risk management techniques and standards to be applied to the project

    B. Act as a central record of information relating to the identified risks for the project

    C. Act as a repository for informal issues

    D. List the responsibilities for achieving an effective risk management procedure

  • Question 9:

    Which role is responsible for creating Checkpoint Reports?

    A. Senior Supplier

    B. Team Manager

    C. Change Authority

    D. Project Support

  • Question 10:

    Which is a task of product-based planning?

    A. Identify activities and dependencies

    B. Write the Project Product Description

    C. Prepare the Work Packages

    D. Produce Product Status Accounts

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.