What product records any time tolerances agreed between the Project Manager and Team Manager?
A. Product Description
B. Work Package
C. Project Initiation Documentation D. Stage Plan
Which is part of quality control?
A. Document the project's acceptance criteria in the Project Product Description
B. Define the quality responsibilities of those involved in the production of the products
C. Produce quality records to show that the planned quality activities have been carried out
D. Maintain the corporate organization's quality management system
Which of the following describes a use of a Configuration Item Record?
A. To record how changes to a product will be controlled
B. To provide information on the approval procedure for the Work Package
C. To record the history of a product
D. To pass responsibility for the delivery of a product to a Team Manager
Identify the missing words in the following sentence.
At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
A. Stage Plan
B. Communication Management Strategy
C. Follow-on action recommendations
D. Quality Management Strategy
Which of the following are true statements about a Project Brief?
1.
Used to provide a foundation for the Initiating a Project process
2.
Created in the Starting up a Project process
3.
Used by the Project Board to make an assessment of a project's progress
4.
Used as the basis of the Project Initiation Documentation
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Which is a purpose of the Quality theme?
A. Establish how the project will ensure that all products created meet their requirements
B. Establish quality assurance to maintain the quality management system
C. Identify all the products of the project to ensure the scope has been adequately defined
D. Determine the communication needs of the organization's quality assurance function
Which is an objective of the Initiating a Project process?
A. Develop the corporate quality management system as part of the Project Initiation Documentation
B. Prepare the plans for the subsequent stages
C. Summarize how the organization's project management method will be tailored for the project
D. Request authority from corporate management to deliver the project
Which is the Change Authority role permitted to authorize?
A. Risks to the project
B. Adjustments to the limits on the change budget
C. Changes to stage tolerance
D. Changes to the project that do not exceed a defined budget
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
Which is NOT obtained from a product's Product Description?
A. The product's quality criteria
B. Who will approve the product
C. The quality method to be used
D. The development method to be used
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.