Which is a true statement about PRINCE2 event-driven controls
A. Event-driven controls take place at predefined periodic intervals
B. Event-driven controls are produced at the frequency defined in a Work Package
C. Event-driven controls are used for decision making
D. Checkpoint Reports are event-driven controls
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
A. controls
B. products
C. project management team
D. stages
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities
A. change budget
B. project budget
C. project's cost tolerance
D. project's risk tolerance
Why is it crucial that the Project Product Description clearly defines acceptance methods?
A. Enables Project Assurance to authorize quality activities
B. Defines how all project products will be reviewed and approved
C. Defines how it will be proven that the completed project product meets the customer's expectations
D. Provides confirmation that all project products have met their quality criteria
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project
Which statement about the quality review technique is FALSE?
A. It enables a check to be made on a product's fitness for purpose
B. It defines the quality responsibilities of the project team
C. It supports the management of future changes by providing a baseline for a product
D. It is used to gain wider acceptance of a product by involving key interested parties
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.
Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders.
2.
Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Which is NOT one of the PRINCE2 integrated elements?
A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PR2F exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.